Construction of Social Dormitory. Stages


9 June 2016. Разместил: saby
Construction of social dormitory for leavers of boarding schools in Aktobe city is in progress.

For the past four months favorable conclusions of complex independent expertise on the main design estimate documentation of the project and external supply lines were received. Corresponding notifications of start-up production of installation and construction works in the local State Architectural and Construction Supervision Authority were registered. Preparatory works of top soil territory clearing were carried out, the land parcel fencing was fixed, temporary communication lines of necessary power were installed. The development of excavations and concrete blinding were fulfilled to 100%.

At present the works of foundation installation of 4 living blocks and one office block are being carried out.